Thanks for choosing Liberty Homes! We are excited to provide you with this progress report on your home that is being built in our Parkside Towns at Westgate community in Bluffdale. Sit back and watch your home be built from the comfort of your home. Use the SHARE buttons above to post photos to your social media accounts!


November 14, 2017

Exterior landscape complete with grass! Inside, cabinets will be delivered this week!

 


November 7, 2017

Hardi-board has been installed with the rock and stucco on the outside. Inside, the doors and trim and finish carpentry has been completed. It’s really taking shape!


October 31, 2017

Rock is being installed on the front of your unit. It looks great! Inside, mud and tape is complete. Next: doors and trim.


October 23, 2017

Insulation is in and exterior is wrapped. Interior: Drywall is up!! Next step: Mud and tape.


October 17, 2017

Insulation is in and drywall and mud and tape has been delivered. Next: hang the drywall.


October 10, 2017

4-way time! If you haven’t already, you will be meeting the superintendent onsite to go over your plan in detail and check the rough electrical, plumbing, HVAC and framing. You have a house!


October 2, 2017

Rough electrical is starting inside and plumbing is close behind.  It is great to be able to walk through the home now! Soon all the trades will be working inside.


September 21, 2017

Frame is up, roof is on! You have a house!  The major trades are getting roughed in. Looks great!


September 12, 2017

The second story is getting a roof! Soon you’ll see the whole structure. It’s exciting!


September 5, 2017

Framing progress continues, now on the second floor!  Building 4 units at once takes time, but soon it will all be up!


August 29, 2017

The framing continues on the first floor! Stay tuned. :)

 


August 23, 2017

The framing has started, the exciting time has begun. Your home will take shape in no time!


August 15, 2017

Your foundation walls are poured, and we’ve backfilled around the foundation. Next up: wait for the concrete to cure so the framing crew can come.


August 8, 2017

We have damproofed the foundation, and window wells are in! Next, backfill.


August 1, 2017

No more empty hole! Your foundation walls are poured, and we will soon put in your window wells, rough plumbing, and backfill around the foundation.


July 21, 2017

Footing forms are here! Next up: pour concrete.


July 14, 2017

Congratulations, we have officially broken ground! Your hole has been dug. Soon you’ll have a foundation!